Bellevue City Hall
Client: City of Bellevue
Location: Bellevue, WA
Size: 350,000 sq. ft.
Project Value: $85 Million

Completion Date: 2006
Scope: Construction Management & Owner's Representative
Architect: SRG Partnership, Inc.
GCCM: Lease Crutcher Lewis
Hainline served as both the Project Manager and Owner’s Representative for the City of Bellevue for their Bellevue City Hall Project. Bellevue City Hall was an $85 million, fast-track project, one of the first public projects to utilize the General Contractor/ Construction Manager (GCCM) project delivery method. The project involved the renovation of the former Qwest Headquarters from an opaque mass into a welcoming, tranformative public facility that contains a variety of programmatic needs for the City’s array of services and amenities.
​
Tasks included managing the project schedule, guaranteed maximum price (GMP) contingency budgets, cost allocation matrices, subcontracting plan, value engineering efforts during construction, and providing project management/owners representative services within the GCCM general conditions and contract.
​
​
bottom of page